Work is full swing for the work scheduled for the renovation work included in the life safety /mechanical update project that is occurring at Twin Ridge. The new chiller is up and running and is cooling the building nicely! Anticipated delivery dates for the new wall mounted fin tube units in all of the classrooms were accelerated slightly so the final heating work should be completed by the first day of school as well. The new fire sprinkler system within the building is completed and the contractor is currently installing the new water main to the building to complete the connection.