Work is full swing for the work scheduled for the renovation work included in the life safety /mechanical update project that is occurring at Bertha Barber. The new chiller unit has been placed and new interior fan coil units have arrived on site for installation. The fire sprinkler system piping is 90% completed at this time. Work on this project is on schedule for substantial completion the first week of August.