Work is full swing for the work scheduled for the renovation work included in the life safety /mechanical update project that is occurring at LeMay. Demolition work is ongoing on various mechanical and building components to prepare for new planned work. New fire sprinkler mains are being run through the building in addition to wireless network wiring. The new chiller has arrived at the site and connections to the main building system will be occurring over the next month. The new fire service water main is also being laid into the building for the new fire sprinkler system. New LED lighting in the gym has been completed and new LED security lighting around the perimeter of the building is ongoing. Work on this project is on schedule for substantial completion the first week of August. Look for further updates as work progresses through the summer months.